top of page

How to draw Activity on Arrow using critical path method

The Critical Path Method (CPM) is a powerful project management tool used to schedule a set of project activities. It helps identify the sequence of tasks that directly affect the project completion time. In the Activity on Arrow (AOA) diagramming method, activities are represented as arrows, and events (or milestones) are represented as nodes. This visual structure aids in analyzing and optimizing project timelines.


Steps to Apply CPM Using AOA

1. List All Activities

Prepare a list of all project activities, including:

  • Activity identifiers (e.g., A, B, C)

  • Duration of each activity

  • Immediate predecessor(s)


Construct the network by following these rules:

  • Draw arrows for each activity from a start event node to an end event node.

  • Ensure that all dependency relationships are clearly represented.

  • Use dummy activities where necessary to avoid ambiguity.



    gjyghuyg




EARLY START (ES): The earliest date a task can start.

EARLY FINISH (EF): The earliest date a task can be completed

LATE START (LS): The latest date a task can start without delaying the project end date

LATE FINISH (LF): The latest date a task can finish without delaying the project end date


Determine:

  • Earliest Start Time (EST): the earliest time an activity can begin.

  • Earliest Finish Time (EFT): EST + duration.

Start from the initial event node and work forward:

  • EST for an activity = maximum EFT of all its predecessors.

  • EFT = EST + activity duration.


    4. Backward Pass (Calculate Latest Times)

    Determine:

    • Latest Finish Time (LFT): the latest time an activity can finish without delaying the project.

    • Latest Start Time (LST): LFT − duration.

    Start from the final event and work backward:

    • LFT for an activity = minimum LST of all its successors.

    • LST = LFT − activity duration.



    • What are the Earliest and Latest time in Network Diagram (CPM)

      How to calculate the Earliest and Latest Time in Network Diagram (CPM) 



Comments


Subscribe to get updated

Thanks for subscribing!

1651429847763.jpg
bottom of page